<_stephen_>
I don't recall seeing anything in the updates that was relevant the last time I read it... I may have missed something.
<lkcl>
_stephen_, the dates are nonsense, they're there because crowdsupply asked for them
<lkcl>
until absolutely every single one of the ducks is absolutely 100% without fail absolute 100% guaranteed lined up it is flat-out impossible to have any kind of schedule, at all.
<lkcl>
example: how can you have a schedule when you have absolutely no idea if there is a source of DDR3 RAM, anywhere in the wworld?
<lkcl>
example: how can you have a schedule if you have absolutely no idea if the PCB coming back from pre-production prototyping is going to work?
<lkcl>
yeah?
<lkcl>
you understand?
<lkcl>
*WHEN* all the components are at the factory
<lkcl>
*WHEN* the pre-production prototype has been signed off
<lkcl>
*WHEN* the factory has told me what their availability is like
<lkcl>
*WHEN* the test rig has been created
<lkcl>
*THEN* and *ONLY* then can a schedule be set
<lkcl>
you understand?
<lkcl>
the next update will be out shortly, it's with crowdsupply at the moment.